Baillet-en-France (95)
Rond-Point du Fayel
Rue Bouffémont
95560 Baillet-en-France
GPS coordinates :
49.0550194, 2.2890186
Backfilling an active underground quarry
Types of layout
Securing the underground quarry
Issues :
Site security
Project presentation
Securing the Placo® quarry in Baillet-en-France by recycling excavated soil. The Baillet-en-France quarry has an outdoor platform for unloading excavated soil trucks. ECT is in charge of transportation and backfilling operations.
ECT’s expertise enables it to offer the carrier :
- management of the backfill authorization process, with the dual aim of accommodating the largest possible volume of soil and optimizing the diversity of soil types used,
- management of all backfilling operations at the quarry (safety, productivity, traceability and environment),
- commercial management with building and civil engineering contractors to negotiate the terms and conditions of soil inputs,
- land logistics management, including the installation of a double freight system.
Key figures
2022
New customer experience, open platform
2021
Platform construction work
Project life
Customer innovation
March 2022 – A new earth unloading platform is installed. This platform makes soil unloading safer and simpler, and saves time: 10 minutes to unload the material. Construction work began in 2021 and lasted 6 months, with various trades working on the platform.
Discovering the galleries
Backfilling the quarry with soil corresponds to a procedure for making the galleries safe once mining has been completed. Backfill comes from construction sites. Land traceability is ensured by ECT.